NOTICE OF DECISION - Conditional Approval
 
Planning Board, Town of New Boston
 
You are hereby notified that the Site Plan Application for Joseph & Allison McGrail, to operate a photography home business from 570 s.f. of the existing dwelling at 243 Mont Vernon Road, Tax Map/Lot #11/31, in the Town of New Boston, has received conditional approval by majority vote of the members of the Planning Board on June 12, 2007, on the motion(s):
 
-       I MOVE to approve the site plan for Joseph & Allison McGrail, to operate a photography home business from 570 s.f. of the existing dwelling at 243 Mont Vernon Road, Tax Map/Lot #11/31, subject to:
 
CONDITION(S) PRECEDENT:
  1. Submission of a minimum of three (3) copies of the revised site plan that include all checklist corrections and any agreed-upon conditions from this hearing;
  2. Execution of a Site Review Agreement regarding the condition(s) subsequent;
  3. Revised driveway permit from New Hampshire Department of Transportation.
  4. Receipt of approved sign location from New Hampshire Department of Transportation.
The deadline for complying with the condition(s) precedent shall be August 15, 2007, the confirmation of which shall be an administrative act, not requiring further action by the Board. Should compliance not be confirmed by the deadline date, and a written request for extension is not submitted prior to that date, an administrative NOTICE OF DENIAL shall be issued without further action of the Board being required.
 
CONDITION(S) SUBSEQUENT:
  1. All of the site improvements are to be completed per the approved site plan;
  2. The Town of New Boston Planning Department shall be notified by the applicant that all improvements have been completed, and are ready for final inspection, prior to scheduling a compliance hearing on those improvements, a minimum of three (3) weeks prior to the anticipated date of compliance hearing and the opening of the business on the site;
  3. Any outstanding fees related to the site plan application compliance shall be submitted prior to the compliance hearing;
  4. A compliance hearing shall be held to determine that the site improvements have been satisfactorily completed, prior to releasing the hold on the issuance of Permit to Operate or Certificate of Occupancy, or both.